| February
2005 |
Compliance
Team is formed |
| April
22, 2005 |
Team
begins review of draft reports |
| December
16, 2005 |
Team
concludes review of draft reports |
| January
15, 2006 |
Completed
Compliance Certification Document is submitted to Leadership
Team |
| January,
2006 |
Final
editing of Compliance Certification Document |
| February,
2006 |
Materials
(printed copies, CDs, website) finalized for submission to SACS |
| March
1, 2006 |
Compliance
Certification Materials submitted to SACS |
| May
15-19, 2006 |
Off-site
Peer Review conducted |
| June
2006 |
Phone
report from SACS on findings of off-site team |
| September
18-October 27, 2006 |
Visitation
by On-Site Team |
| June
20-22, 2007 |
Review
by Commission on Colleges |